City Attorney City Clerk City Council City Treasurer Directory of Govt Officials Employment Information Judicial Court System Mayor's Office Other Local Jurisdictions State & Federal Government
Arts & Entertainment Civic Organizations Community Access - Channel 10 Events and Festivals Granite City Township Healthcare History of Granite City Landlord Training Library District Neighborhood Watch Park District Public Transportation Recycling School District Service Organizations Sports & Recreation Street Maintenance Transportation & Distribution Waste Disposal Worship
Comptroller Economic Development Emergency Management Fire Department IT Department Neighborhood Improvement Police Department Public Works Risk Management Wastewater Treatment
Action Line Community Calendar Online Documents
Adopt-A-Street Program Calendar City Employment Contact Information Facts and Figures Frequently Asked Questions Local News Media Maps Moving To Granite Safety Information St. Louis Area Attractions Tax Information Where Can I Find A Job? Zoning Information
From the Mayor's Desk General Announcements Job Postings RFPs & RFQs Road Construction Updates
    City Hall  |  Community  |  Departments  |  E-Government  |  Information  |  News & Events     Printable Version
   Search:  

    Contact the Mayor
    Contact My Councilmember
    Review the City Budget
    Read about the History of the City
    Review Council Meeting Agendas
    Read Council Meeting Minutes
    Read about City Council Policies
    Look up Ordinances
    Run for Office
    Request Public Records

 
   MAYOR Ed Hagnauer

   News & Press Releases

   Mayor's Priorities

   Mayor's Biography


  City Hall

  City of Granite City
  2000 Edison Avenue
  Granite City, IL 62040     Map


  Contact Form

  Have a general comment
  or question?     Use this form

To view current Amber and SARAA Alerts,
Click Here

 View Expired Alerts


 
    City Hall


  See a listing of
  City Events and
  Public Meetings.

  View Calendar >>



City Hall > Mayor's Office > From the Mayor's Desk

From the Mayor's Desk


January 2008

PONTOON ROAD OVERPASS PROJECT


  1. Project Description
    • Pontoon Road – The existing highway-rail grade crossing will be replaced with a new structure carrying Pontoon Road over the tracks of the NS, KCS (GWWE), and UP, as well as Illinois Route 203 Nameoki Road (IL 203). Due to this construction, the following intersections along Pontoon Road will be closed: Mitchell Avenue, Braden Avenue, Melrose Avenue and Briarcliff Drive. All of these intersections are located west of the existing Pontoon Road grade crossing. With closure of the aforementioned intersections, the following new roadways will be constructed: an extension of Briarmoor Lane between Briarhaven Drive and Century Drive; a connector roadway between Pontoon Road and Old Alton Road, a connector roadway between Rode Avenue and Braden Avenue (all located west of the existing Pontoon Road grade crossing); and, a connector roadway between IL 203 and North Street, located east of the existing IL 203/Pontoon Road highway intersection. The following streets and alleys will be improved or reconstructed: Pontoon Road; IL 203; Rode Road; Briarhaven Drive; North Street; Amos Avenue; and the north/south alley between Manley Avenue and Amos Avenue. Traffic signals will be installed at the following intersections; Briarhaven Drive/Pontoon Road; North Street/IL 203; and North Street/Pontoon Road. Various drainage improvements will also be made to accommodate this construction.

    • 22nd Street Crossing – The City will vacate the roadway on both sides of the existing 22nd Street highway-rail grade crossing. Following vacation of the roadway, the railroads will remove the existing crossing surfaces and the City will erect barricades to prevent vehicular traffic from entering railroad right-of-way. The 22nd Street grade crossing will not be closed and barricaded until the new Pontoon Road Overpass is complete and open to vehicular traffic. Various drainage improvements will also be made to accommodate the construction in this area.

    • 20th Street Crossing – Century Drive will be extended from 22nd Street to 20th Street; 20th Street will be re-aligned to accommodate trucks and other vehicles that will utilize the Century Drive Extension. The following intersections will be reconstructed; Illinois Avenue/20th Street; and Century Drive Extension/20th Street. The extension of Century Drive also requires the removal and replacement of NS’s Yard Office building. Various drainage improvements will also be made to accommodate the construction in this area. (refer to Century Drive Extension drawings)

  2. Will Pontoon Road be closed during construction of Phase 2?
    • Yes, however a detour roadway (2 lane) will be constructed just north of the existing roadway (refer to attached drawing).

  3. What will happen to the big dirt piles?
    • They will be moved over and used as fill along the existing Pontoon Road.

  4. During construction, who will address individual problem and concerns?
    • The City will have a Resident Engineer who will serve as the City’s liaison with the contractor. This Resident Engineer will have a field trailer on site during construction.

  5. How long will the project take?
    • This project is being constructed in 2 phases. Phase 1 is nearing completion and Phase 2 has been bid and the award is pending. Phase 2 is scheduled to begin construction in spring 2008. Phase 2 has 234 working days (a normal construction season has 117 working days) and therefore is anticipated to be completed in 2009.

October 2007

Welcome Back Downtown


The City of Granite City is about to embark on a new and exciting time in the Downtown area. The first phase of the Niedringhaus Streetscape project, which is looking quite marvelous, has been completed and the second phase will soon be underway. We are also getting closer to the groundbreaking of our new four-screen movie theater, which is projected to be open for business by the second quarter of 2009. Also, the Old Press-Record Building is in the process of undergoing a transformation that will change it into a new Youth Center/Sports Complex for our City’s young people. In addition, our new camera system and increased police presence has caused more than a 60% reduction in crime in the downtown area.

The funding for these new improvements has been provided through the Downtown Tax Increment Financing (TIF) District, which was established in 1986. It is a source of revenue that has been generated only by our downtown businesses, such as Walgreens, McDonald’s, Quik Trip and Gateway Regional Medical Center among many others, all located in the downtown area. The redevelopment of the downtown area, which will include new renovations throughout the downtown area over the next six years, is only possible because of the likes of those above mentioned businesses.

It is important for me to note, however, that because this TIF money was generated by downtown area businesses, it can only be spent on improvements in the downtown area. If this were a general revenue source that could be spent anywhere throughout the City, we promise that we would spend it improving the overall infrastructure of the City, beginning with repaving every street in town. Since this is not possible, we have developed a budgeting plan that will allow us to repave every block in the City by 2023 and then continually repave each street at least once every 15 years thereafter.

Until then, I hope that you and your family will begin to be able to enjoy Downtown Granite City once again, which is improving every day.

Do you want to share your thoughts and/or suggestions concerning the City's efforts to redevelop the downtown area. If so, click here.




Last Updated On: Jan 8th, 2009 at 10:39 AM



Privacy Policy | Disclaimer | Map | Contact Us Created and Hosted by   Wildfire Internet  |  Granite City, IL